Cranleigh Leisure Centre logoCranleigh Leisure Centre

Milestones

  • Council commitment to multi million pound investment

    2018

     

    -

     

    2019

    The Sport, Leisure and Culture Consultancy (SLC) were appointed to conduct an Options Appraisal to explore the alternative site options for development of a new leisure facility in Cranleigh.
  • Council put all corporate projects on hold due to Covid-19 pandemic

    2020

     

    -

     

    2021

    In September 2021 a Feasibility Update Report was undertaken by SLC to test the conclusions from the earlier, pre-pandemic Options Appraisal. The findings confirmed that the facility mix, and preferred location identified within the 2019 Options Appraisal still stood.
  • Revised capital budget approved

    October 2023

     

    -

     

    November 2023

    On 17 October 2023 Waverley Borough Councillors approved a revised capital budget of £31,137,252, to deliver a new build low carbon leisure centre built to Passivhaus certification standards in Cranleigh.
  • Concept and design development

    2023

     

    -

     

    Early 2024

    Ideas, surveys, design workshops and discussions. Appointment of GT3 architects, Project Board and Project Working Group.
  • Sharing the design

    March 2024

     

    -

     

    April 2024

    Sharing the design with the community, online, in person and at drop in session events. Comments will help inform the planning application.
  • Planning submission

    May 2024

     

    -

     

    August 2024

    Planning application and associated reports will be submitted to Waverley Borough Council for consideration.
  • Planning decision

    August 2024

     

    -

     

    October 2024

    The project team hope to have a planning decision by Autumn 2024.
  • Construction starts on site

    Spring 2025

     

    -

     

    Autumn/Winter 2026

    Hoping to start construction in 2025. Subject to procurement processes and of course the planning decision.
  • New leisure centre opens!

    Winter 2026

     

    -

     

    Spring 2027

    Opening details to be shared nearer the time.....we are hoping it all goes to plan, but with any large development there can be hold ups along the way.....
  • Old leisure centre demolished

    Winter 2026

     

    -

     

    Spring 2027

    Demolition of the existing leisure centre and final landscaping of the site.